Skip Navigation
This table is used for column layout.
South Windsor Town Seal
Welcome to South Windsor, CT
Bottom of Town Seal

Search Our Site
 
Treatment Plant Upgrade
Archived
Updated 9-24-10

081910 020.jpg

081910 036.jpg

081910 043.jpg

083110 037.jpg

083110 038.jpg

083110 039.jpg

083110 041.jpg

083110 043.jpg

083110 047.jpg

083110 049.jpg

083110 060.jpg

083110 064.jpg

083110 067.jpg

083110 069.jpg

Updated on 7-7-2010:

Administration Bld. Boiler Room 5-21-10.jpg
Administration Building Boiler Room

Administration Bld. Roofing 5-5-10.jpg
Administration Building Roofing

Administration Bld. Work Shop Area 5-5-10.jpg
Administration Building Work Shop

Aeration Tank Concrete Stair 5-28-10.jpg
Aeration Tank Concrete Stair

Asbestos Abatement @ Incinerator 5-5-10.jpg
Asbestos Abatement at Incinerator

Blower Bld. Blower Room 5-21-10.jpg
Blower Building Blower Room

CL&P Installs new Pole 5-11-10.jpg
CL&P Installs New Pole

Electric Wireway @ Secondary Clarifier Pump Station 5-11-10.jpg
Electric Wireway at Secondary Clarifier Pump Station

Electrical Conduit Installation @ MCC 9&10 Pad 5-28-10.jpg
Electrical Conduit Installation at MCC 9&10 Pad

Electrical Manhole #44 5-11-10.jpg
Electrical Manhole #44

Entry Canopy @ Admin. Bld. 5-11-10.jpg
Entry Canopy at Administration Building

Exhaust Fans @ Admin. Bld. Roof 5-5-10.jpg
Exhaust Fans on Administration Building Roof

Folding Partition Track & Motor 5-5-10.jpg
Folding Partition Track & Motor

Hatch @ Secondary Clarifier Pump Station 5-28-10.jpg
Hatch at Secondary Clarifier Pump Station

Incinerator Demolition 5-28-10.jpg
Incinerator Demolition

Installing Wood Blocking @ Blower Bld. Roof 5-11-10.jpg
Installing Wood Blocking on Blower Building Roof

Masonry IN-fill @ Admin. Bld. Doorway D-06 5-11-10.jpg
Masonry IN-fill in Administration Building Doorway D-06

Painting @ Admin. Bld. Boiler Room 5-28-10.jpg
Painting Administration Building Boiler Room

Process Pipe @ Secondary Clarifier Pump Station 5-28-10.jpg
Process Pipe in Secondary Clarifier Pump

Roofing Work @ Blower Bld. 5-11-10.jpg
Roofing Work on Blower Building

Secondary Clarifier 3 & 4 Pump Station 5-28-10.jpg
Secondary Clarifier 3 & 4 Pump Station

Secondary Clarifier Pump Station 5-11-10.jpg
Secondary Clarifier Pump Station

Stormwater Outfall Header & Rip Rap 5-11-10.jpg
Stormwater Outfall Header & Rip Rap

Transformers Delivered @ Blower Bld. 5-21-10.jpg
Transformers Delivered at Blower Building

Update: April 19, 2010

Administration Bld. Plumbing Work 3-3-10.jpg
Plumbing Work in the Administration Building


Administration Building Brick Work 3-15-10.jpg
Brick Work in the Administration Building


Aeration Tank Effluent Area 3-9-10.jpg
Aeration Tank Effluent Area


Aeration Tank Handrails 3-3-10.jpg
Aeration Tank Handrails


Aeration Tank Weir Gates 3-16-10.jpg
Aeration Tank Weir Gates


Aerial View Looking Northwest 4-1-10.jpg
Aerial View Looking Northwest


Aerial View Looking Southwest 4-1-10.jpg
Aerial View Looking Southwest


Blower Bld. Containment Walls 3-3-10.jpg
Blower Building Containment Walls


Blower Building Staged for Masonry Work 3-9-10.jpg
Blower Building Staged for Masonry Work


Conference & Lunch Rooms @ Admin. Bld. 3-9-10.jpg
Conference and Lunch Rooms at the Administration Building


Ductbank  #21 South of Aeration Tank 3-9-10.jpg
Ductbank #21 South of Aeration Tank


Electrical installation @ Aeration Tank 3-31-10.jpg
Electrical Installation at the Aeration Tank


Electrical Manholes 13, 14 & 48 3-16-10.jpg
Electrical Manholes 13, 14 and 48


Electrical Manholes & Ductbank 3-3-10.jpg
Electrical Manholes and Ductbank


Interior Masonry @ Admin. Bld. 3-3-10.jpg
Interior Masonry at the Administration Building


Internal Recycle Pump Control 3-31-10.jpg
Internal Recycle Pump Control


Masonry Starting @ Blower Building 3-31-10.jpg
Masonry Starting at the Blower Building


New Administration Bld. Brick Work 3-31-10.jpg
New Administration Building Brick Work


New Administration Building Work 3-3-10.jpg
New Administration Building Work


Plant Water Hydrant @ Sec. Clarifier 3-31-10.jpg
Plant Water Hydrant at Secondary Clarifier


Plant Water Pipe South of Secondary Clarifier 3-31-10.jpg
Plant Water Pipe South of Secondary Clarifier


Secondary Clarifier #3 Equipment 3-3-10.jpg
Secondary Clarifier #3 Equipment


Secondary Clarifier #4 3-31-10.jpg
Secondary Clarifier #4


Secondary Clarifier Effluent Pipe & Gate Valves 3-31-10.jpg
Secondary Clarifier Effluent Pipe & Gate Valves


Sludge Storage Tank Area 3-3-10.jpg
Sludge Storage Tank Area


Temporary Heat @ Administration Bld. 3-3-10.jpg
Temporary Heat at the Administration Building


Winter Protection @ Administration Bld. 3-3-10.jpg
Winter Protection at the Administration Building

Update: 11/20/09

The landscape at the town’s wastewater treatment plant is going through major changes!  
The walls of the new aeration tanks (where the bugs that break down the wastewater grow) are now complete.
one_small.jpg

These are the 24” pipes that will move water to the new aeration tanks.  There will be a total of 6.
two_small.jpg

The large pipe is one of 4 pipes that will transport water from the aeration tanks to the secondary clarifiers.
three_small.jpg


The two large pipes are part of an internal recycling system for the new aerators that returns partially treated wastewater to the beginning of the treatment process
four_small.jpg

The new secondary clarifiers are nearing completion of the concrete work. (These are the tanks where fine solids in the water settle out. (Clear water left in the upper part of the tanks will be collected in channels to be constructed where the two workers are standing and get discharged to the Connecticut River.
five_small.jpg

six_small.jpg

The wall that forms one side of the new pipe gallery needs to be waterproofed and caulked.
seven_small.jpg

Initial construction activities have also started on the new blower building.  The blowers will provide air for the microorganisms in the aeration tanks.
eight_small.jpg

This is some of the conduit that carries wiring for power and fiber optic cables for communications into the blower building.
nine_small.jpg

The new sludge storage building is where thickened solids removed from the wastewater will be stored prior to disposal.
ten_small.jpg

There is a room (pipe gallery) running the length of the building where pumps and piping will be installed.
eleven_small.jpg

The walls of the pipe gallery also need to be caulked and waterproofed.
twelve_small.jpg

There are three tanks which will hold approximately 30,000 gallons (each) of the thickened solids (sludge).
thirteen_small.jpg

The green pipes entering the side of the tanks are for pressure relief valves that open into the storage tanks.  They relieve the pressure of ground water that might be under the tanks and could cause them to crack.
forteen_small.jpg

Work has started on the Administration/Garage building.  This building will hold the plant’s laboratory, administrative offices, workshop, employee facilities, parts storage as well as the garage for some of the plant’s vehicles.
fifteen_small.jpg

Treatment Plant Construction Trivia:
  • Over 3,000 cubic yards of concrete have been poured!  (That’s enough concrete to make three, four-foot wide sidewalks the length of Sullivan Avenue…)
  • In excess of 600,000 pounds (300 tons) of reinforcing steel (rebar) has been used so far!  (That’s the same as 171 bright yellow Corvettes or 682 Harley motorcycles.)
  • Approximately 125,000 feet (almost 24 miles!) of underground conduit (piping that wire is run through) will be used on the project! (That’s enough conduit to stretch the length of Pleasant Valley Road - from Main Street to Manchester - 81/2 times.)



Update: October 27, 2009
Activity is increasing as construction at the treatment plant goes forward.  As things progress the scope of the new plant becomes more apparent and impressive.  It’s big!  From the plant entrance on Vibert Road to what will be the back of the plant compound is almost 900 feet.
tpupgrade_small.jpg
Our new aeration system is almost 200 feet and about 90 feet wide.  Each of the two tanks will hold 600,000 gallons of water.
The first picture was taken inside one of the tanks, from near the back end.
1026_02_small.jpg
This picture shows plant operator Dave Geng looking at the inside of the distribution chamber at the beginning of the new aeration tanks.
1026_03_small.jpg
Coring of holes in the existing aeration tanks and pipe installation between the existing tanks and the new aerators has also begun.  These pipes will carry water to the new aeration tanks.  The old tanks are going to be modified in support of the new treatment process we’ll be using.
1026_04_small.jpg
Our new secondary clarifiers will certainly be a welcome addition.  They’re 65 feet in diameter (10 feet larger than our current tanks) and hold almost 350,000 gallons each.
The top photo shows the rebar mat for the tank base being “woven”.  The second picture shows the tanks with about 90% of the tank walls poured and cured.
1026_05_small.jpg
1026_06_small.jpg
The new sludge storage tank structure is well underway.  The base is completely poured and reinforcing steel for the walls is being put up.
1026_07_small.jpg





Update: September 22, 2009

Construction continues at the treatment plant!  Over the past several weeks 80% of the aeration tanks bases have been completed, while the side and center walls are springing up.

Aeration Tanks
001.jpg

The secondary clarifier bases are being prepped and the 24” center piping for the #3 clarifier is in place and encased in concrete.
002.jpg

A double rebar mat will be woven on top of the stone to strengthen the concrete tank base, which will be poured in the next couple weeks.
Also, excavation has progressed on the new sludge storage building, with geofabric and stone being put in place.
003.jpg

This building, as its name suggests, is where thickened, liquid sludge will be stored prior to its removal for off site disposal.  The liquid sludge will be hauled to the MDC plant in Hartford where it will be dewatered and incinerated.
As construction progresses, the number of different activities is increasing.  The contractor is beginning to do some work inside the existing plant compound.  Submittals for equipment and materials come in daily for review, comment and approval.  There are requests for information (RFI’s) from the contractor asking for clarification about drawings and specifications.  There are also meetings with the contractor and construction engineers in preparation for the coming weeks activities as well as working on system development.
Upcoming activities include forming and pouring the center walkway for the aeration tanks and completing the rebar mat for one of the new secondary clarifiers and pouring the concrete base.
The sludge storage building will become an area of increased activity, too.  This structure will be more complex, somewhat similar to the new pump gallery that will be built between the two new secondary clarifiers.  It will contain three enclosed storage tanks as well as pumping facilities.
There is also the possibility that work will start on the administration/garage building.  There will be modifications to the interior of the existing building that will encompass a new laboratory for water quality testing and process control, and a new addition that will provide a much needed workshop, electrical shop and parts storage area.

Things are looking up!
clip_image002.jpg




Update: August 3, 2009

Despite the inclement weather, the Treatment Plant construction is progressing well!  In June the site was cleared and silt fence installed around the plant to protect the wetlands. July was a busy month of site work and excavating for the new aeration tanks* and secondary clarifiers**.
An initial eight feet of material (soil) was removed and transported off site.  Because of the final depth of the tanks and the height of the local water table (we’re so close to the Connecticut River), fourteen wells were installed around the site.  These wells pump excess water from the digging area.  This allowed the contractor (C.H. Nickerson) to remove an additional three feet of material, reaching the final depth of the tanks.
Geofabric (similar to heavy landscaping fabric) was spread across the tank area. One foot of stone was spread on top of the fabric for drainage underneath the new tanks.  Iron reinforcing bars (rebar) are currently being installed to form a “mat” on top of the stone.  This rebar mat will help strengthen the concrete tank bases.
Although somewhat involved, forming the rebar mat should go quickly.  Nickerson is hoping to start pouring the concrete tanks bases during the second week of August.  They are also going to be working on the excavation for the new sludge storage building (the deepest excavation of the project!) and possibly begin the excavation for the new air blower building.
* Two new aeration tanks, each approximately 40 feet wide, 13 feet deep and 160 feet long are being constructed.  The treatment plant uses a biological process to break down solids and certain chemical compounds from the wastewater (for the past 15 months, the treatment plant has removed 96% of these).  The aeration tanks are the home for the bacteria and protozoa that perform this process.
** Two new secondary clarifiers are being added to the treatment plant.  Water from the aeration tanks flows into these 65 foot diameter tanks where solids settle and are removed.  The clear water from these tanks (the plant’s final effluent) then flows through a metering chamber and is discharged to the Connecticut River.

++++++++++++++++ Help Yourself and the Treatment Plant!! ++++++++++++++
Washing grease down the drain or introducing rags and debris into the sewer system can cause big problems!  They can plug up your pipes, block the sewer lines or jam our pumps.  Any of these can cause sewage to back up into your or your neighbor’s home!  Grease also interferes with the plant process, making it more difficult to clean the water!

Site Clearing and Aeration Tank and 2ndry Excavation 017.jpg     Site Clearing and Aeration Tank and 2ndry Excavation 032.jpg     Site Clearing and Aeration Tank and 2ndry Excavation 046.jpg
Site Clearing and Aeration Tank and 2ndry Excavation 047.jpg     Site Clearing and Aeration Tank and 2ndry Excavation 062.jpg
Site Clearing and Aeration Tank and 2ndry Excavation 063.jpg     Site Clearing and Aeration Tank and 2ndry Excavation 065.jpg     Site Clearing and Aeration Tank and 2ndry Excavation 078.jpg

For more information, contact the South Windsor Public Works Department
at 860-644-2511 ext. 243.
This site will be updated throughout the construction project. Stay Tuned!




June 23, 2009
Ground Breaking Event
IMG_3943.jpg

IMG_3901.jpg 6242009_31519_0.jpg IMG_3914.jpg
IMG_3932.jpg IMG_3937.jpg IMG_3938.jpg
IMG_3920.jpg IMG_3944.jpg IMG_3961.jpg



 
Return to Home Page
Spacer
Spacer
Virtual Towns & Schools Website